[av_one_full first min_height=” vertical_alignment=” space=” custom_margin=” margin=’0px’ padding=’0px’ border=” border_color=” radius=’0px’ background_color=” src=” background_position=’top left’ background_repeat=’no-repeat’ animation=” mobile_breaking=” mobile_display=”] [av_textblock size=” font_color=” color=” av-medium-font-size=” av-small-font-size=” av-mini-font-size=” admin_preview_bg=”]
[/av_textblock] [/av_one_full][av_heading tag=’h1′ padding=’10’ heading=’Modular Pathology Lab’ color=” style=’blockquote modern-quote’ custom_font=” size=’42’ subheading_active=’subheading_below’ subheading_size=’15’ custom_class=” admin_preview_bg=” av-desktop-hide=” av-medium-hide=” av-small-hide=” av-mini-hide=” av-medium-font-size-title=” av-small-font-size-title=” av-mini-font-size-title=” av-medium-font-size=” av-small-font-size=” av-mini-font-size=”] Fort Meade, MD[/av_heading] [av_one_half first min_height=” vertical_alignment=” space=” custom_margin=” margin=’0px’ padding=’0px’ border=” border_color=” radius=’0px’ background_color=” src=” background_position=’top left’ background_repeat=’no-repeat’ animation=” mobile_breaking=” mobile_display=”] [av_textblock size=” font_color=” color=” av-medium-font-size=” av-small-font-size=” av-mini-font-size=” admin_preview_bg=”]

The Challenge

The United States Army was in need of renovating the Hospital located at one of their facilities at Ft. Meade, MD. Their plans were to relocate part of the facility to a temporary space as the hospital underwent renovations.[/av_textblock] [/av_one_half] [av_one_half min_height=” vertical_alignment=” space=” custom_margin=” margin=’0px’ padding=’0px’ border=” border_color=” radius=’0px’ background_color=” src=” background_position=’top left’ background_repeat=’no-repeat’ animation=” mobile_breaking=” mobile_display=”] [av_textblock size=” font_color=” color=” av-medium-font-size=” av-small-font-size=” av-mini-font-size=” admin_preview_bg=”]

The Solution

Modular Genius built this customer a 3,600 sq ft Modular Pathology Lab Building. The temporary swing space was a fully functional medical facility with administrative space. The installation was complete in 90 days from award to occupancy.[/av_textblock] [/av_one_half]

A Case Study

Modular Pathology Lab

Related

Case Studies